A458 Road Closure Update.
Below is a fortnight look ahead giving details of the forthcoming road closures associated with the Bridgnorth Bypass Project.
20:00 4th September to 06:00 5th September
- Kidderminster Roundabout East side closed for resurfacing operations.
- No access/egress onto A458 towards Stourbridge.
- Local diversion in place via A442 Kidderminster Road and Stourbridge Road.
- All other roundabout exits/entries are open to traffic.
20:00 5th September to 06:00 6th September
- Ludlow Road Roundabout South side closed for resurfacing operations.
- No access/egress onto B4364 towards Ludlow.
- Diversion in place via the B4368, the B4368, the A458 and the A49.
- All other roundabout exits/entries are open to traffic.
20:00 6th September to 06:00 7th September also
20:00 7th September to 06:00 8th September
- The A458 (bypass) between the Kidderminster Road Roundabout and the Ludlow Road Roundabout will be closed for resurfacing operations.
- Diversion in place via town centre, the B4364, the B4373 and the A442.
20:00 8th September to 06:00 9th September
- Ludlow Road Roundabout North side closed for resurfacing operations.
- No access/egress onto B4364 towards Bridgnorth Town Centre.
- Local diversion in place via Wenlock Road and the B4364 Ludlow Road.
- All other roundabout exits/entries are open to traffic.
20:00 11th September – 06:00 12th September also
20:00 12th September to 06:00 13th September also
20:00 13th September to 06:00 14th September also
20:00 14th September to 06:00 15th September also
20:00 15th September to 06:00 16th September
- The A458 (bypass) between the Kidderminster Road Roundabout and the Ludlow Road Roundabout will be closed for resurfacing operations.
- Diversion in place via town centre, the B4364, the B4373 and the A442.
20:00 15th September – 06:00 16th September
- Kidderminster Roundabout East side closed for resurfacing operations.
- No access/egress onto A458 towards Stourbridge.
- Local diversion in place via A442 Kidderminster Road and Stourbridge Road.
- All other roundabout exits/entries are open to traffic.
Hedd Wyn Jones
Senior Engineer