Bridgnorth Bypass Road Update & Look Ahead (2017-11-17)

Bridgnorth Bypass Road Update & Look Ahead (2017-11-17)

A458 Improvement update Improvement works on the A458 Bridgnorth bypass are set to be substantially complete on 21st November. At present the contractor is completing the last of the programmed works, with works in progress on powering up the streetlights, the vehicle restraint system, gully cleaning and the white lining. The additional resurfacing works on the Stourbridge Road Roundabout is also still in progress with white lining the final activity. These works should be completed by Tuesday 21st November. However any…

Read More Read More

Bridgnorth Bypass Road Update & Look Ahead (2017-11-10)

Bridgnorth Bypass Road Update & Look Ahead (2017-11-10)

A458 Improvement update Improvement works on the A458 Bridgnorth bypass are set to finish on 21st November. Works to the deck joints on Bridgnorth River Severn Bridge, signage and drainage are now complete.  Works to the safety barriers and street lighting are coming to and end. The additional works identified to be carried out to the Stourbridge Road Roundabout are planned to begin week commencing 13th November over a series of two consecutive night time, and two consecutive 24hour road closures….

Read More Read More

Bridgnorth Bypass Road Update & Look Ahead (2017-11-03)

Bridgnorth Bypass Road Update & Look Ahead (2017-11-03)

A458 Improvement update Improvement works on the A458 Bridgnorth bypass continue. Works to the deck joints on Bridgnorth River Severn Bridge are now complete. Works to the safety barriers, street lighting and drainage over the entire site are still ongoing. These works will continue through November during midweek daytime hours. This will involve further periods where both the Ludlow Road Roundabout, the Kidderminster Road Roundabout and the Wenlock Road Junction may be controlled under traffic signals at various times. These…

Read More Read More

Bridgnorth Bypass Road Update & Look ahead 27/10/17

Bridgnorth Bypass Road Update & Look ahead 27/10/17

A458 Improvement update Improvement works on the A458 Bridgnorth bypass continue. Works to the safety barriers, street lighting and drainage over the entire site are still ongoing. These works will continue through November during midweek daytime hours. This will involve further periods where both the Ludlow Road Roundabout, the Kidderminster Road Roundabout and the Wenlock Road Junction may be controlled under traffic signals at various times. These signals are being manually controlled at peak times. When the Kidderminster road roundabout…

Read More Read More

Bridgnorth Bypass Road Update & Look ahead 13/10/2017

Bridgnorth Bypass Road Update & Look ahead 13/10/2017

A458 Improvement update Improvement works on the A458 Bridgnorth bypass continue. Works to the safety barriers, street lighting and drainage over the entire site have been ongoing. These works will continue until November during midweek daytime hours. This will involve further periods where both the Ludlow Road Roundabout, the Kidderminster Road Roundabout and the Wenlock Road Junction will be controlled under traffic signals at various times. These signals are being manually controlled at peak times. When the Kidderminster road roundabout…

Read More Read More

Bridgnorth Bypass Update 7th Sept 2017

Bridgnorth Bypass Update 7th Sept 2017

A458 Improvement update Improvement works on the A458 Bridgnorth bypass continue. The work on the A458 and the roundabout approaches between the A458/B4373 (Wenlock Road) junction and the Stourbridge Road roundabout remain due to finish by 10 November. Works to the safety barriers, street lighting and drainage over the entire site have been ongoing. These works will continue into the beginning of October during daytime hours. This will involve further periods where both the Ludlow Road Roundabout, the Kidderminster Road…

Read More Read More

Bridgnorth Bypass Update 4th Sept 2017

Bridgnorth Bypass Update 4th Sept 2017

A458 Road Closure Update. Below is a fortnight look ahead giving details of the forthcoming road closures associated with the Bridgnorth Bypass Project. 20:00 4th September to 06:00 5th September Kidderminster Roundabout East side closed for resurfacing operations. No access/egress onto A458 towards Stourbridge. Local diversion in place via A442 Kidderminster Road and Stourbridge Road. All other roundabout exits/entries are open to traffic. 20:00 5th September to 06:00 6th September Ludlow Road Roundabout South side closed for resurfacing operations. No access/egress onto B4364 towards…

Read More Read More

Bridgnorth Bypass Update 1st Sept 2017

Bridgnorth Bypass Update 1st Sept 2017

A458 Improvement update Improvement works on the A458 Bridgnorth bypass continue. The work on the A458 and the roundabout approaches between the A458/B4373 (Wenlock Road) junction and the Stourbridge Road roundabout are due to finish by 10 November. Works to the safety barriers, street lighting and drainage over the entire site have been ongoing. These works will continue into the beginning of October during daytime hours. This will involve further periods where both the Ludlow Road Roundabout, the Kidderminster Road…

Read More Read More

Bridgnorth Bypass Update 19/7/17

Bridgnorth Bypass Update 19/7/17

A458 Improvement works have started. Improvement works on the A458 Bridgnorth bypass started on Tuesday 11 July 2017. The work on the A458 and the roundabout approaches between the A458/B4373 (Wenlock Road) junction and the Stourbridge Road roundabout are due to finish by 10 November. A 20mph temporary speed limit has been placed on the works extents for the duration of the scheme. This speed reduction is in place to protect both the contractors workforce, but also to give added…

Read More Read More

B4364 Bridgnorth to Neenton roadworks: 8-12 May 2017

B4364 Bridgnorth to Neenton roadworks: 8-12 May 2017

Following a traffic collision earlier this year, extensive damage was caused to a safety barrier at Faintree. As a safety measure, temporary traffic signals have been in place since the incident whilst a new barrier has been both designed and manufactured. In order to install the new barrier, the road will need to be closed for a short period. This has been planned for 8 May to 12 May 2017. The section of the B4364 to be closed will be between the Bridgnorth…

Read More Read More

A458 Bridgnorth Bypass Night Closure 11-13 Apr

A458 Bridgnorth Bypass Night Closure 11-13 Apr

Please find attached details of forthcoming road closure Road to be closed: A458 Bridgnorth by-pass/ River Severn Bridge  Date and duration: 2 x night closures – 11/04/17 13/04/17 8pm to 6am Purpose: Bridge deck joint survey Applicant: Shropshire Council Bridges and structures team Diversion: Through Bridgnorth If you have any questions, or require any further information please contact the Street Works Team on streetworks@shropshire.gov.uk

Roadworks: B4364 Junction Of Oldfield 21st Feb

Roadworks: B4364 Junction Of Oldfield 21st Feb

B4364 B4364 From Faintree Hall Farm To Lower Cockshutt Farm 21 February — 21 February Delays likely Traffic control (multi-way signals) Works location: At Junction Of Oldfield Works description: Proving And Cabling Only Responsibility for works: BT

Roadworks: Eudon Burnell lane closure

Roadworks: Eudon Burnell lane closure

The council have just heard from Highways that the Eudon lane at the B4363 end will probably be closed within the next day or so and will remain closed until the bridge work is completed.  During that time, access to all properties will be available from the B4364.  Highways are still investigating who is responsible for the closure board which has appeared – no one has made application to close the lane although they think it is connected with the fibre optic broadband…

Read More Read More

Roadworks Pre-Warning: Road Closure Ludlow Road, Bridgwalton Farm Junction to Milfields Way Junction – early March

Roadworks Pre-Warning: Road Closure Ludlow Road, Bridgwalton Farm Junction to Milfields Way Junction – early March

Advance warning for Road Closures on the B4364 Ludlow Road 2nd March to the 4th March 2016 for Pre Surface Dressing Patching, and disruption through to 10th March –  Bridgwalton Farm Junction to Milfields Way Junction More details on the interactive map – set search to “next three months”    

Roadworks: B4364 – Faintree Hall Farm – 16-18/11/15

Roadworks: B4364 – Faintree Hall Farm – 16-18/11/15

B4364 B4364 From Lower Faintree To Faintree Hall Farm, Faintree, Bridgnorth, Shropshire 16 November — 18 November Traffic control (two-way signals) Delays likely due to Streetworks 8m Road Crossing In Tarmac Road For New Supply at Os Driveway To Faintree Hall Responsibility: Western Power Distribution

Roadworks: Neenton Churchyard Farm Jct : 18-20 Jan

Roadworks: Neenton Churchyard Farm Jct : 18-20 Jan

Road Closure : The Pheasant, Neenton ( Side road to Wrickton ) 18th – 20th January Roadworks, Delays Likely 18th – 20th January – Churchyard Farm Junction With B4364 Neenton To Wrickton Mannor Junction, Wrickton, Bridgnorth, Shropshire.  WORKING OUTSIDE CHURCHYARD FARM AT THE JCN OF B4364 FROM CLEE BROOK BRIDGE TO NEW HOUSE FARM JUNCTION Ref: LB501A5W/11214448Q Responsibility: Severn Trent Water

Roadworks: Ditton Priors 14/10/15

Roadworks: Ditton Priors 14/10/15

Chapel Lane, Ditton Priors, Shropshire 14 October — 14 October Traffic control (Stop/Go boards) Delays possible due to Streetworks Overhead Works Only – No Excavation For Switching Service Between Poles at Outside Chapel Cottage, 102 Meters From The Juction With Hall Road Ditton Priors Responsibility: Western Power Distribution EToN status: Planned work about to start

Roadworks: Ditton Priors 20-22/10/15

Roadworks: Ditton Priors 20-22/10/15

Oakwood Road, Ditton Priors, Bridgnorth, Shropshire 20 October — 22 October Traffic control (two-way signals) Delays likely due to Streetworks Locate And Excavate 1 Blockage In Existing Duct at Oakwood Road, From North – West Of Sawmill Entrance To 20m South – East Of Sawmill Entrance. Responsibility: BT EToN status: Planned work about to start

Roadworks: B4364 Neenton 12-16 Oct

Roadworks: B4364 Neenton 12-16 Oct

B4364 From Clee Brook Bridge To New House Farm Junction, Neenton, Bridgnorth, Shropshire 12 October — 16 October Traffic control (two-way signals) Delays likely due to Streetworks Install 158m Of One Way Poly Duct In Carriageway. at Opposite All Saints Church To Approximately 156 Meters North East, B4364 From Clee Brook Bridge To New House Farm Juncti Responsibility: BT EToN status: Planned work about to start

Roadworks: B4364 Faintree 7-11th Sept

Roadworks: B4364 Faintree 7-11th Sept

  B4364 From Clee Brook Bridge To Lower Faintree, Faintree, Bridgnorth, Shropshire 07 September — 11 September Traffic control (two-way signals) Delays likely due to Streetworks Install 130m Of 1 Way Poly Duct In Verge,Install 35m Of 1 Way Poly Duct In Carriageway at Adjacent Bank Farm To Approximately 159 Meters North East, B4364 From Clee Brook Bridge To Lower Faintree Responsibility: BT EToN status: Planned work about to start

Roadworks: Station Road, Ditton Priors 26-28 Aug

Roadworks: Station Road, Ditton Priors 26-28 Aug

Station Road, Ditton Priors, Shropshire 26 August — 28 August Traffic control (give & take) Delays possible due to Streetworks 10m Trenching In Tarmac Footway And Grass Verge For New Supply at Opposite Wychwood Responsibility: Western Power Distribution EToN status: Planned work about to start

Roadworks: B4364 Chetton 24/8 – 4/9

Roadworks: B4364 Chetton 24/8 – 4/9

Roadworks, delays likely 24 Aug – 4 Sep Location: B4364 From Lower Cockshutt Farm To Chetton Grange Junction, Chetton, Bridgnorth, Shropshire Traffic lights, etc: Traffic control (two-way signals)Information for Operational Teams Description: LAY 154M OF BT DUCT BETWEEN EXISTING BOXES IN CARRIAGEWAY AND VERGE AND PERFORM X2 COREDRILLS  